Disconnection of all cables to including but limited to; Sensors (Humming, Speed & vibration), combustion equipment and thermocouple, as needed for the disassembly of GT
Disconnection of Fire Fighting cable as needed to remove the enclosure roof
Fact finding of instruments and cables and updating replacement or repair reports
Preparation of items for assembly prior to handover
Re-assembly of instruments and cable as per the marked or referenced position
Testing of all the sensors before closing the casings like bearing casing, combustion chamber instrument etc., after reconnection and making sure the functionality.
Providing the final report
Required Experience & Skills -
Must hold Power plant experience, ideally within large CCPP projects
5+ years working on power plant outages with skillset covering inspection, factfinding, service and maintenance
Ability to carry out the full electrical disassembly and reassembly of gas and steam turbine electrical components